Bypass Traffic Update as of January 9

Bypass Traffic Update as of January 9

Here is the latest road restrictions and construction work along the Regina Bypass Route.

 

Pinkie Road Detour

A portion of the north bound lane of Pinkie Road – near the Highway 1 overpass –  will be closed until January 26, weather permitting. The closure is needed to erect girders and precast deck panels on the new bridges along the south portion of Pinkie Road.

 

Traffic will be detoured down the South Service Road to Highway 1 http://www.reginabypass.ca/new-pinkie-road-detour-updated/

 

 

Hauling

Between Hwy 6 and TR 164 until April, weather permitting  

Stockpiling of sand at Park Street Stockpile

Hauling operation using TR164 from Hwy 6 to Park Street as haul road.

Day and Night operation

(TCRF-918)

 

Indian Head to Harle Pit until end of January

The trucks will use Hwy 35 to Highway 1 West. The trucks will then turn on Highway 734 and travel a short distance before turning into our Bypass compound to drop-off their load.

(TCRF-917)

 

Hwy 1 West near Pinkie Road until January 30, weather permitting

Work will be done adjacent to the roadway

Expect temporary shoulder closures

Temporary westbound and east bound lane closures

(TCRF-919)

 

Please Note:  All Bypass truck cover their load when hauling materials. 

 

 

Highway 1 West

Piling and Structure Work

Temporary west bound lane restriction near Pinkie Road off ramp

Work will be done adjacent to the road

Minor delays due to speed reduction

 

Highway 1 West and Pinkie Road

Bridge Work

Temporary lane restrictions and GTH Detour

Work will be done adjacent to the road

Minor delays due to speed reduction

(TCRF- 520 and 521)

 

Highway 33

Bridge Work

Temporary lane restrictions

Work will be done adjacent to the road

Minor delays due to speed reduction

(TCRF- 601)

 

Mainline between Highway 1 East and Highway 33

Bridge Work

Temporary lane restrictions

Work will be done adjacent to the road

Minor delays due to speed reduction

(TCRF- 902)

 

 

Highway 1 East at Pilot Butte

Bridge Work

Temporary lane restrictions

Work will be done adjacent to the road

Minor delays due to speed reduction

(TCRF- 911)

 

Highway 1 East 

Sign installation – on going

Work adjacent to the road

Minor delays due to speed reduction

TCRF-907 and 766)

 

Pilot Butte Bridge

Completion of Diverging Diamond – Ongoing

Work adjacent to the road

Single Lane alternating traffic

Minor delays due to speed reduction

(TCRF-822 and TCRF-885)

 

Pinkie Road south of Hwy 1 

24-hour equipment crossing

Minor delays due to speed reduction

On going

(TCRF-540)

 

Hwy 1 East of Highway 48

Work on new westbound off ramp to existing Hwy 1

Intermittent lane closures

Minor delays due to speed reduction

(TCRF-402)

 

Hwy 6 near Hwy 6 Detour  

24-hour Truck Hauling

Crossing roadway

Minor delays due to speed reduction

24-hour operation

(TCRF-727)

 

Range Road 164 near Hwy 6 

24-hour equipment crossing

Minor delays due to speed reduction

On going

(TCRF-709 and 918)

 

Dewdney Avenue – between Pinkie Road and Condie Road 

24-hour equipment crossing

Minor delays due to speed reduction

My have traffic control team on site

24-hour operation

(TCRF-238)

 

Hwy 1 at Condie Road near South West off-ramp

24-hour equipment crossing

Minor delays due to speed reduction

On going

(TCRF-917)

 

For the latest traffic restrictions related to the construction of the Regina Bypass, please follow Regina Bypass Partners on Twitter @reginabypass and regularly check the Highway Hotline at www.hotline.gov.sk.ca.

 